DETAILS OF WORKS UNDER EXECUTION
Sl. No. |
Name of Work |
G.O.Ms.No. AS RAS |
Expr. Upto 03/11 |
Expr. During 2011-12 |
Date of Commencement |
Scheduled date of completion |
Present stage of work |
||
Expr. Upto previous month (09/11) |
Expr. During the mongh (10/11) |
Total Expr. |
|||||||
1 |
Construction of Check Dam across Thamiraparani river in Vallanadu village of Srivaikundam Tk in Thoothukudi district. |
G.O.No.50/PW(R2)Dept. Dt:23.02.11 Rs.450 (lakhs) |
– |
– |
– |
– |
– |
-- |
Tender received and under scrutiny in Superintending Engineer Office, Thirunelveli. |
2 |
Construction of Check dam across the Karumeniyar river in Manapadu village of Tiruchendur taluk of Thoothukudi District. |
G.O.No.50/PW(R2)Dept. Dt:23.02.11 Rs.66.00 lakhs |
– |
– |
– |
– |
– |
-- |
Site handed over on 25.08.2011 Work to be started. |
3 |
Construction of Check dam across the Karumeniyar river in Muthaloor village near Thangaikulam village of Sathankulam Taluk of Thoothukudi district. |
G.O.No.51/PW(R2)Dept. Dt:23.02.11 Rs.52.30 lakhs |
– |
– |
– |
– |
– |
– |
Site handed over on 25.08.2011 Work to be started. |
|
IAMWARM PHASE – III WORKS |
|
|
|
|
|
|
|
|
4 |
Rehabiliation and Modernisation of tanks, anicut and supply channel in Kovilpatti Taluk |
G.O.No.81/PW(WR1)Dept. Dt:09.03.10 Rs.181.33 lakhs |
6.18 |
61.63 |
‘0.00 |
61.63 |
21.02.2011 |
20.05.2012 |
47% of work completed. Remaining work is in progress. |
5 |
Rehabiliation and Modernisation of tanks, anicut and supply channel in Ottapidaram Taluk |
G.O.No.81/PW(WR1)Dept. Dt:09.03.10 Rs.52.56 lakhs |
8.42 |
19.98 |
12.27 |
32.25 |
24.02.2011 |
23.02.2012 |
72% of work completed. Remaining work is in progress. |
6 |
Rehabiliation and Modernisation of tanks, anicut and supply channel in Ottapidaram & Srivaikundam Taluk |
G.O.No.81/PW(WR1)Dept. Dt:09.03.10 Rs.107.12 lakhs |
‘17.60 |
43.53 |
24.25 |
67.78 |
25.02.2011 |
24.02.2012 |
76% of work completed. Remaining work is in progress. |
7 |
Rehabiliation and Modernisation of tanks, anicut and supply channel in Ottapidaram Taluk |
G.O.No.81/PW(WR1)Dept. Dt:09.03.10 Rs.113.95 lakhs |
‘15.22 |
41.52 |
28.21 |
69.73 |
25.02.2011 |
24.02.2012 |
70% of work completed. Remaining work is in progress. |
8 |
Rehabiliation and Modernisation of Korampallam Surplus course in Kalangarai village of Thoothukudi District. |
G.O.No.81/PW(WR1)Dept. Dt:09.03.10 Rs.252.87 lakhs |
‘1.50 |
21.09 |
177.01 |
‘198.60 |
‘07.07.2011 |
‘06.07.2012 |
70% of work completed. Remaining work is in progress. |
Sd/- xxxx
Executive Engineer, WRO/PWD,
Korampallam Aru Basin Division,
Thoothukudi.
WRO/PWD
Korampallam Aru Basin Division Thamiraparani Basin Circle,
Thoothukudi Tirunelveli.
DETAILS OF WORK PROPOSALS IN THOOTHUKUDI DISTRICT
Sl. No. |
Name of Work |
Estimate Amount |
Remarks |
|
|
Anti Sea Erosion Works: |
|
|
|
1 |
Construction of Rubble Mound Sea Wall in Vivekanander colony at Saveiryarpuram village in Thoothukudi District. |
97.00 lakhs |
Estimate submitted to the chief Engineer, Desgin Reasrch and Construction Support, Chennai vide Chief Engineer, WRO/PWD, Madurai Region, Madurai lr.no.OT3/AE5/ASE/96/ dt:24.10.10 for getting Administrative approval from Government. |
|
2 |
Construction of Rubble Mound Sea wall at Inigo Nagar at Thoothukudi District. |
138.00 lakhs |
Estimates submitted to Chief Engineer, Plan Formulation, Chennai for getting approval under 13th Finance Commission |
|
3 |
Construction of Groyne at Alanthalai village in Thiruchendur Taluk of Thoothukudi District. |
14.34 Crores |
||
4 |
Construction of Training wall at Punnakayal Village in Thiruchendur Taluk of Thoothukudi District. |
8.47 Crores |
||
|
Check Dam Proposals: |
|||
1 |
Construction of a checkdam across korampallam River near Veeranayakanthattu village of Thoothukudi Taluk of Thoothukudi District. |
153.00 lakhs |
Estimate submitted to chief Engineer, WRO/PWD, Madurai Region, Madurai. |
|
2 |
Construction of a Check dam across Thamiraparani River near Vallanadu village Down stream side of River Bridge in Srivaikundam Taluk of Thoothukudi District. |
430.00 lakhs |
Estimates submitted to Chief Engineer, Plan Formulation, Chennai. |
|
3 |
Construction of a check dam across Karumaniyar River near Adaikalapuram in Sathankulam Taluk of Thoothukudi District. |
70.00 lakhs |
Estimate prepared by P&D Thoothukudi Sub division and submitted to Chief Engineer, Plan Formulation, Chennai. |
|
4 |
Construction of Check Dam across uppodai near Savalaperi village in Kovilpatti Taluk of Thoothukudi District. |
86.00 lakhs |
Estimate prepared by P&D Tirunelveli Sub division and submitted to Chief Engineer, Plan Formulation, Chennai.
|
|
5 |
Construction of Check Dam across uppar odai near Kombadi in Savarimangalam Village, Ottapidaram Taluk of Thoothukudi District. |
45.00 lakhs |
Estimate prepared by P&D Thoothukudi. |
|
6 |
Construction of Check Dam across Korampallam river in Umarikottai Village of Thoothukudi District. |
45.00 lakhs |
Estimate prepared by P&D Thoothukudi. |
|
7 |
Construction of check dam across Karumaniyar river near Mani Nagar in Sathankulam Taluk of Thoothukudy District. |
56.00 Lakhs |
Estimate prepared by P&D Thoothukudi Sub division and submitted to Chief Engineer, Plan Formulation, Chennai. |
|
8 |
Construction of Check dam across Chekkarakudi Odai near Ramasamypuram Village of Thoothukudy Taluk of Thoothukudy District |
WRO / PWD52.00 Lakhs |
Estimate resubmitted to the Superintending Engineer after attending the remarks for including the work under JC rain water surface Plan scheme. |
|
9
|
Construction of check dam across Kallar river near Therkkukalmedu Village in Ottapidaram Taluk of Thoothukudy District. |
84.00 Lakhs |
Estimate resubmitted to the Superintending Engineer after attending the remarks for including the work under JC rain water surface Plan scheme. |
|
10 |
Construction of check dam across Kallar river near Adhanoor Village in Ottapidaram Taluk of Thoothukudy District. |
57.00 Lakhs |
Estimate resubmitted to the Superintending Engineer after attending the remarks for including the work under JC rain water surface Plan scheme. |
|
|
NEW TANK FORMATION PROPOSALS: |
|
|
|
1 |
Formation of New tank across the jungle odai in Valasamudram Village of Thoothukudy District. |
|
Estimate prepared by P&D Thoothukudi Sub division and submitted to Chief Engineer, Plan Formulation, Chennai. |
|
Sd/- xxxx
Executive Engineer, P.W.D/W.R.O
Korampallam Aru Basin Division,
Thoothukudi.